This is in continuation of the earlier series of questions for Management Yogi's Primavera P6 Pro Live Lessons video course.
I'll definitely suggest that you take both the question parts together, while you attempt the questions. This way you will have continuation in your learning and get a better understanding on the kind of questions to be faced in your assessment at the end of Primavera P6 Pro Live Lessons course.
Also, as mentioned in the previous part, to answer these questions, you need to have:
- Solid understanding of Primavera P6 software in managing teams and projects.
- Out of the box usage of Primavera P6 project management capabilities, which can be used in a variety of scenarios and situations.
- Basic understanding of traditional project management.
- Critical thinking, logical reasoning, ability to think out of the box and also answering questions with speed and accuracy.
These questions are taken from the course: Primavera P6 Pro Live Lessons Online Course. This course comes with full money-back guarantee, applicable for the entire course duration. In other words, there are no terms and conditions (T&Cs). Use the course and if you don't like, I'll refund the money any time.
Again, I hope you enjoy doing these questions and it helps in your learning Primavera P6.
[This series - Part - 1]
*********
Question – 7: For which activity types resources cannot be added?
A Task Dependent and Level of Effort (LOE)
B Level of Effort (LOE) and WBS Summary
C Start Milestone and Finish Milestone
D WBS Summary and Start Milestone
Question – 8: For your project, one of the senior team members has prepared the work breakdown structure (WBS). It’s shown below. How many elements are at Level – 3 for the WBS?
A Five
B One
C Four
D Can’t be determined
Question – 9: The default calendar which can be set for a project can only be:
A Corporate Standard – Full Time
B Trades – 5 Days Work Week
C Custom Project Calendar
D Any Global Calendar
Question – 10: While formatting the columns in your custom layout, you have added these columns: Activity ID, Activity Name, Planned Duration, Remaining Duration as well as Start and Finish. It’s shown below. Which two fields should you add to know the delay you can have for an activity without delaying the early start of the successor and the project’s end?
A Total Float and Activity Float
B Free Float and Total Float
C Constraints and Deadline
D Lead and Lag
Question – 11: Which one of the following is not a correct % complete type used in Primavera P6?
A Activity % Complete, Duration % Complete, Resource % Complete
B Physical % Complete, Units % Complete, Duration % Complete
C Performance % Complete, Activity % Complete, Units % Complete
D Schedule % Complete, Performance % Complete, Cost % Complete
Question – 12: Primavera P6 calculates considering Duration, Units and Units/Time. However, the Units/Time setting can be shown as a percentage or as units per duration. Considering hour per day is set at 10 hours, what will be the Units/Time for 2.25 hours in percentage terms?
A 22.5%
B 50%
C 40%
D 37.5%
*********
The question set is available in the embedded document below. The answers are also part of this document. You can scroll to see the content.
For all answers, subscribe to this site and send a mail (from your GMail id) to managementyogi@gmail.com.
You May Also Like:
1. Frequently Asked Questions (FAQs) - Primavera P6 Pro Live Lessons, by Satya Narayan Dash
2. Primavera P6 Pro Live Lessons Online Course, by Satya Narayan Dash
3. Install, Set-up, Run and Test Primavera P6 P6 Professional R22.x/R24.x, by Satya Narayan Dash
No comments:
Post a Comment
Sign- or Log-in and put your name while asking queries in comments. Any comment is welcome - comments, review or criticism. But off-topic, abusive, defamatory comments will be moderated or may be removed.